[DGX Spark] Status of CX7 firmware fix for "eCPRI parser not supported"

Hi NVIDIA Aerial team,

We have installed Aerial CUDA-Accelerated RAN 26-1 on DGX Spark, following the official “Installing Tools on NVIDIA DGX Spark System” guide for the 26-1 release.

We noticed the “eCPRI parser not supported” / “Dynamic flex parser is not supported” warnings on the DGX Spark CX7.

We see that the 26-2 Known Issues still mention “eCPRI flow parser firmware dependency” on DGX Spark, and earlier forum replies said the fix would come with a new NIC firmware.

  1. Does 26-2 solve this problem, or is a new CX7 firmware still required?
  2. If a fixed firmware has been released, what is the version number and where can we download it?

Thanks!

Hi @york4517 ,

Welcome to the forum!

Please take a look at Aerial testbed/DGX Spark: Dynamic flex parser is not supported.

Thank you.

Thanks for the information! That topic mentions the fixed NIC firmware was planned for October.

Is it still on track for October?

Once it’s released, will the DGX Spark install guide be updated with the new firmware version, or will it be announced on the forum?

A quick update here when it’s available would be much appreciated.

Thanks!

Hi @nhashimoto,

I’m also experiencing the following warnings when running NVIDIA Aerial CUDA-Accelerated RAN on DGX Spark:

  • eCPRI parser not supported

  • Dynamic flex parser is not supported

I noticed that NVIDIA recently provided a workaround to obtain ConnectX-7 firmware 28.47.1088 from the DOCA 3.2.1 package in GitHub Issue #68:

Could you please confirm:

  1. Does firmware 28.47.1088 resolve both parser warnings on DGX Spark?

  2. Is this the firmware fix previously expected in October 2026, or is a newer release still planned?

  3. Has this firmware been validated with NVIDIA Aerial 26-1 or 26-2, particularly for O-RAN 7.2x eCPRI fronthaul operation?

I’d like to confirm this before proceeding with the firmware update.

Thanks for your support!

  1. No, 28.47.1088 doesn’t include the fix.
  2. We are targeting to release it within Oct.
  3. No, we have already shipped 26-1 and 26-2. 26-3 will be the official release validated with the new firmware.

Thank you for the clarification!

You mentioned that Aerial 26-3 will be the official release validated with the new ConnectX-7 firmware.

Could you please confirm whether Aerial 26-3 is also expected to be released in October 2026, or whether only the firmware update is planned for October?

As I recall, Aerial 26-2 was released quite recently, so I was a little surprised to hear that 26-3 is already being planned.

Thanks again for your support!

26-3 will be released in Dec.
Our current release cadence is 3 major releases, like X-1/2/3 in April, Aug, and Dec, in a year, and some minor releases, like X-Y.Z.