As mentioned in the article, each scale unit (SU) contains four leaf switches per plane, with each leaf supporting two rails in the following combinations: 1+5, 2+6, 3+7, and 4+8.
I would like to understand why the pairing is not arranged as 1+2, 3+4, 5+6, and 7+8 instead. Is the 1+5, 2+6, 3+7, 4+8 configuration considered a better design? If so, what is the reasoning behind it?
Additionally, assuming that each GPU in the compute cluster is equipped with 8 ConnectX-6 interfaces, and using the MQM9790 switch with MFA7U10 OSFP-to-2x QSFP56 active optical splitter cables (AOC) — which convert 400 Gb/s into 2 × 200 Gb/s — would the leaf layer still require 4 switches per SU? And should the same rail pairing scheme (1+5, 2+6, 3+7, 4+8) be applied to each leaf?
Thank you for your time and clarification.