Production module supply situation

Hello,

the AGX production module seems to have a lead time of 5 months / 24 weeks anywhere we look. In order to develop our product, we would like to get hold of a handful of devices earlier. We can only use dev kits for software development. They cannot be used for hardware development since we need to test our own cooling solution etc. Is there a standard way to solve this from NVIDIA’s side?

I would also be happy with some old 16GB modules, or used devices in general. If there’s someone who knows someone, hit me up :)

1 Like

We are having challenges with various components and are working continuously to address the issue. In meantime, if you are building a commercial product might want to consider our partner systems if they have inventory.

This topic was automatically closed 60 days after the last reply. New replies are no longer allowed.